Groundbreaking,
July 3, 2008 |
 |
Start of Digging,
July 7, 2008 |
 |
|
Elevator Shaft Start,
July 17, 2008 |
 |
Elevator Shaft forms,
July 22, 2008 |
 |
|
Poured
Foundation,
July 25, 2008 |
 |
Poured Foundation,
July 25, 2008 |
 |
|
Profile of a Knot-Holer,
July 25, 2008 |
 |
Prep for pouring lower wall
July 29, 2008 |
 |
|
Poured lower
walls
August 1, 2008 |
 |
Backfilling
lower wall
August 5, 2008 |
 |
|
Prep beam pockets
August 12, 2008 |
 |
Hard hat time
August 15, 2008 |
 |
|
Steel Framework
Hard hat time
August 15, 2008 |
 |
Steel Framework
Hard hat time
August 15, 2008 |
 |
|
Framework for stairs in
place
August 19, 2008 |
 |
Fire stairs framing,
August 20, 2008 |
 |
|
Steel framework with roof
beams,
August 25, 2008 |
 |
Fire stairs with
poured concrete,
August 29, 2008 |
 |
|
Final concrete pour, main
floor,
September 3, 2008 |
 |
Stairways to the Stars,
September 4, 2008 |
 |
|
Preparing
for Shell
Installation,
Sept. 12, 2008 |
 |
Preparing
for Shell
Installation,
Sept. 15, 2008 |
 |
|
Partial Tower
Enclosure,
Sept. 22, 2008 |
 |
Partial Tower
Enclosure,
Sept. 22, 2008
|
 |
|
Partial Tower
Enclosure,
Sept. 23, 2008 |
 |
Completed Shell Enclosure
Sept. 30, 2008 |
 |
|
Elevator Shaft from the top,
Sept 30, 2008 |
 |
Split Block Siding,
Sept. 30, 2008 |
 |
|
Brick work in progress,
October 8, 2008 |
 |
Completed Shell plus brick
work,
October 10, 2008 |
 |
|
Completed Split Block
Siding, October 10, 2008 |
 |
Topping off some brick work,
October 14, 2008 |
 |
|
Shell with brick work,
November 1, 2008 |
 |
Stucco side
November 7, 2008 |
 |
|
Smith St. side,
November 7, 2008 |
 |
Entry way to tower,
November 7, 2008 |
 |
|
3rd Floor,
connection to BRAM,
April 13, 2009 |
 |
2nd Floor,
connection to BRAM,
April 13, 2009 |
 |
|
1st Floor,
connection to BRAM,
April 13, 2009 |
 |
Anita Alic
takes air hammer
to 1st flr opening,
April 13, 2009 |
 |
|
Wright crew with Georgia and
Linda,
April 13, 2009 |
 |
More Air
Hammer,
April 13, 2009 |
 |
|
Georgia Brehm
helps Anita with
1st flr opening,
April 13, 2009 |
 |
Full Connection
into Cellar,
April 24, 2009 |
 |
|
Georgia and Linda checkout
1st flr access,
June 2, 2009 |
 |
Wright workers prepare
threshold,
June 2, 2009 |
 |
|
Elevator Wing Portico
Entrance,
June 2, 2009 |
 |
Elevator Wing Entrance Door,
June 2, 2009 |
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|